| December 23, 2011 |
 |
| Ongoing exterior construction |
|
|
 |
| Ongoing works at the main lobby |
|
|
| |
 |
| Finishing works on the 5th floor deck parking |
|
|
 |
| 12th floor hallway |
|
|
| |
 |
| Residential unit on the 12th floor Unit K |
|
|
|
|
| |
| December 1, 2011 |
 |
| Ongoing exterior construction |
|
|
 |
| Ongoing façade works |
|
|
| |
 |
| Ongoing works at the main lobby |
|
|
 |
| Ongoing works at Swimming Pool & Amenity Area |
|
|
| |
 |
| Finishing works on the 10th floor corridor |
|
|
 |
| Ongoing interior finishing works at the 16th Floor |
|
|
|
| |
| November 1, 2011 |
 |
| Ongoing exterior construction |
|
|
 |
| Ongoing works at the Lobby |
|
|
| |
 |
| Ongoing works at Carpark |
|
|
 |
| Ongoing works at Swimming Pool & Amenity Area |
|
|
|
| |
| October 1, 2011 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the Lobby |
|
|
| |
 |
| Elevator at the Lobby |
|
|
 |
| Ongoing works at Carpark |
|
|
| |
 |
| Ongoing works at Swimming Pool & Amenity Area |
|
|
 |
| Ongoing interior works at the 16th Floor |
|
|
| |
 |
| Ongoing interior works at the 16th Floor |
|
|
 |
| Ongoing interior works at the 16th Floor |
|
|
|
| |
| September 1, 2011 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the Lobby |
|
|
| |
 |
| Elevator at the Lobby |
|
|
 |
| Ongoing works at Carpark |
|
|
| |
 |
| Ongoing works at Swimming Pool & Amenity Area |
|
|
 |
| Ongoing interior works at the 10th Floor |
|
|
| |
 |
| Ongoing interior works at the 10th Floor |
|
|
 |
| Ongoing interior works at the 10th Floor |
|
|
|
| |
| August 5, 2011 |
 |
| View along Legazpi Street |
|
|
 |
| View along Greenbelt 3, ongoing installation works on interior partition and other finishing works |
|
|
|
| |
| July 1, 2011 |
 |
| View along Legazpi Street |
|
|
 |
| View along Greenbelt 3, ongoing installation works on interior partition and other finishing works |
|
|
|
| |
| June 1, 2011 |
 |
| View along Legazpi Street |
|
|
|
|
| |
| April 28, 2011 |
 |
| View along Legazpi Street |
|
|
 |
| View along Greenbelt 3, ongoing installation works on interior partition and other finishing works |
|
|
|
| |
| February 1, 2011 |
 |
| View along Legazpi Street |
|
|
|
|
| |
| January 6, 2011 |
 |
| View along Greenbelt 3, ongoing installation works on interior partition and other finishing works |
|
|
|
|
| |
| December 20, 2010 |
 |
| View along Greenbelt 3, ongoing installation works on interior partition and other finishing works |
|
|
|
|
| |
| October 28, 2010 |
 |
| View along Greenbelt 3, ongoing installation works on interior partition and other finishing works |
|
|
|
|
| |
| September 7, 2010 |
 |
| View along Greenbelt 3, ongoing installation works on interior partition and other finishing works |
|
|
|
|
| |
| July 28, 2010 |
 |
| View along Greenbelt 3, ongoing installation works on interior partition and other finishing works |
|
|
|
|
| |
| June 4, 2010 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 40th Floor, view along Greenbelt 3 |
|
|
|
| |
| April 22, 2010 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 40th Floor, view along Greenbelt 3 |
|
|
|
| |
| March 23, 2010 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 37th Floor, view along Greenbelt 3 |
|
|
|
| |
| February 17, 2010 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 33rd Floor, view along Greenbelt 3 |
|
|
|
| |
| January 6, 2010 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 27th Floor, view along Greenbelt 3 |
|
|
|
| |
| December 22, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 26th Floor, view along Greenbelt 3 |
|
|
|
| |
| November 20, 2009 |
 |
| Construction has reached 22nd Floor, view along Legazpi Street |
|
|
|
|
| |
| October 29, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 20th Floor, view along Greenbelt 3 |
|
|
|
| |
| October 14, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 17th Floor, view along Greenbelt 3 |
|
|
|
| |
| September 17, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Construction has reached 15th Floor, view along Greenbelt 3 |
|
|
|
| |
| August 26, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the 9th level |
|
|
|
| |
| August 12, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the 9th level |
|
|
|
| |
| July 22, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the 8th level |
|
|
|
| |
| July 2, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the 6th level |
|
|
|
| |
| June 18, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the 5th level |
|
|
|
| |
| June 2, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the 4th level |
|
|
|
| |
| May 19, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the 3rd level |
|
|
|
| |
| May 5, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the 2nd level |
|
|
|
| |
| April 16, 2009 |
 |
| View along Legazpi Street |
|
|
 |
| Ongoing works at the mezzanine level |
|
|
| |
|
 |
| Ongoing reinforcement bars work, formworks at Shearwall |
|
|
 |
| Concreted columns of the Ground Floor |
|
|
|
| |
| March 19, 2009 |
 |
| Ongoing works for the Ramp from Basement 1 to Ground Floor and Ground Floor to Mezzanine |
|
|
 |
| Ground Floor Columns and Mezzanine beams, girders and slab |
|
|
| |
|
 |
| Basement 1 |
|
|
 |
| Ongoing works of Slab and Beam at Basement 1 to D Ground Floor |
|
|
|
| |
| February 18, 2009 |
 |
| Continuous Installation of Formworks at Ground Floor |
|
|
 |
| Haul Out of Remaining Excavated Material |
|
|
|
| |
| January 29, 2009 |
 |
| Preparation of rebar for Lean Concreting at partial portion |
|
|
 |
| Preparation of rebar for Lean Concreting at partial portion |
|
|
|
| |
| January 14, 2009 |
 |
| Installation of Rebar |
|
|
 |
| Rebar Fabrication Area at Yakal / Malugay Street |
|
|
| |
 |
First Pouring using chute and pumpcrete |
|
|
 |
| Concrete Sampling |
|
|
|
| |
| December 8, 2008 |
 |
| First Concrete Pouring |
|
|
 |
| First Concrete Pouring |
|
|
|
| |
| December 3, 2008 |
 |
| Propping 2nd Layer - Pipings ready for installation upon completion of Waler |
|
|
 |
| Propping 2nd Layer - Pipings ready for installation upon completion of Waler |
|
|
|
| |
| November 21, 2008 |
 |
| On going Excavation |
|
|
 |
| On going Excavation |
|
|
|
| |
| November 12, 2008 |
 |
| Excavation along GSIS Building Side |
|
|
|
|
| |
| November 6, 2008 |
 |
| Perimeter Fence along Legazpi Steet |
|
|
 |
| Excavation facing Gallardo Street |
|
|
| |
 |
| Excavation along GSIS Building Side |
|
|
 |
| Excavation along GSIS Building Side |
|
|
|
| |
| October 30, 2008 |
|
| |
| October 15, 2008 |
|
| |
| August 26, 2008 |
 |
| Breaking of Parking Area Slab along Gallardo side; Breaking of CR, EE room at UG level. |
|
|
 |
| Hauling out of broken concrete. |
|
|
| |
 |
| Hauling out of broken concrete. |
|
|
|
|
| |
| July 21, 2008 |
|
| |
| July 1, 2008 |
|
| |
| May 21, 2008 |
|
| |
| January 10, 2008 |
 |
| Demolished wall at roof deck along Legazpi Street. |
|
|
 |
| Ongoing Demolition at roof deck. |
|
|
|
| |
| November 29, 2007 |
|