January 1, 2013
Eton Tower Makati
Ongoing installation of formworks and rebars at the Upper Deck 4, Deck 4B and 5th floor
Eton Tower Makati
Ongoing construction on the 5th floor, view along Rufino st.
 
December 1, 2012
ETM
Ongoing construction

ETM
Ongoing construction at Eton Tower Makati (view from Rufino building)
ETM
Ongoing construction (top view)
 

November 1, 2012
ETM
Ongoing installation of formworks and rebars
ETM
Ongoing installation of formworks and rebars
ETM
Ongoing installation of formworks and rebars)
 
 
October 1, 2012
ETM
Ongoing construction (view along V. Rufino St.)
ETM
Ongoing construction at upper Deck 3 and lower Deck 4
ETM
Ongoing installation of formworks and rebars (top view from Dela Rosa corner V. Rufino Sts.)
 

September 1, 2012
ETM
Ongoing construction at Deck 4
ETM
Ongoing exterior works (right side – view along Rufino St.)
ETM
Ongoing construction of shear wall at the ground floor (view from Deck 3)
 
 
August 1, 2012
ETM
Ongoing installation of formworks and rebars on 4th floor
ETM
Ongoing construction (view along V.A. Rufino St.)
ETM
Ongoing construction (view along Dela Rosa St.)
 

July 1, 2012
ETM
Ongoing installation of formworks and rebars on the fourth floor
 

June 1, 2012
ETM
Ongoing construction at the 2nd floor
ETM
First concrete pouring
ETM
Ongoing construction at the 2nd floor
 
 
May 1, 2012
ETM
Ongoing works on the ground floor
ETM
Exterior top view along Dela Rosa Street.
ETM
Exterior top view along Ormaza Street
 
 
April 1, 2012
ETM
Installation of Precast Forms and Rebars on the 2nd Floor
ETM
Chipping of Columns at the Mezzanine
ETM
Installation of Retrofitting Rebars on the Ground Floor Columns
ETM
Ongoing Works at the Mezzanine
 
March 1, 2012
ETM
Construction is now in full swing
ETM
Ongoing construction on the 2nd floor
ETM
Ongoing construction on the ground floor
ETM
Ongoing works at the basement
 
February 01, 2012
ETM
Ongoing retrofitting at the basement
ETM
Ongoing construction at Basement
ETM
Ongoing construction on the 2nd floor
 
 
January 5, 2012
Ongoing construction at Basement
Ongoing construction at Basement
Ongoing construction at Basement
Ongoing construction at Basement
Ongoing construction at Basement