December 23, 2011
Exterior finishing works on Garnet road
Ongoing finishing works at typical floor lobby
 
Ongoing interior finishing works
 
 
December 1, 2011
Exterior finishing works on Garnet road
Exterior finishing works on Sapphire road corner Emerald Avenue
 
Ongoing finishing works at the main entrance
Ongoing finishing works at the main entrance
 
Ongoing works at Swimming Pool & Amenity Area
 
 
November 1, 2011
Ongoing exterior construction
Ongoing construction at the main lobby entrance
 
Ongoing works at Swimming Pool & Amenity Area
Ongoing construction at the residential unit
 
October 1, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
Ongoing works at 36th floor, view along Emerald Avenue
 
Carpark
Swimming Pool
 
Elevator at the 10th Floor
Ongoing interior works at the 10th Floor
 
Ongoing interior works at the 10th Floor
Ongoing interior works at the 10th Floor
 
Ongoing interior works at the 10th Floor
Ongoing interior works at the 10th Floor
 
September 1, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
Ongoing works at 36th floor, view along Emerald Avenue
 
Ongoing interior works the 16th Floor
Ongoing interior works at the 16th Floor
 
Elevator at the 16th Floor
Hallway at the 16th Floor
 
August 5, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
Ongoing works at 36th floor, view along Emerald Avenue
 
July 1, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
Ongoing works at 36th floor, view along Emerald Avenue
 
June 1, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
Ongoing works at 36th floor, view along Emerald Avenue
 
April 28, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
 
 
March 25, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
 
 
February 1, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
 
 
January 6, 2011
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
 
 
December 20, 2010
Ongoing works at 36th floor, view along Emerald Avenue corner Sapphire Road
 
 
October 28, 2010
Ongoing works at 33rd floor, view along Emerald Avenue corner Sapphire Road
 
 
September 7, 2010
Ongoing works at 25th floor, view along Emerald Avenue corner Sapphire Road
 
 
July 28, 2010
Ongoing works at 21st floor, view along Emerald Avenue corner Sapphire Road
 
 
July 7, 2010
Ongoing works at 17th floor, view along Emerald Avenue corner Sapphire Road
 
 
June 16, 2010
Ongoing works at 14th floor, view along Emerald Avenue corner Sapphire Road
 
 
April 22, 2010
View along Emerald Avenue corner Sapphire Road
Ongoing works at 9th floor, view along Emerald Avenue
 
March 23, 2010
View along Emerald Avenue corner Garnet Road
Ongoing works at 6th floor, view along Emerald Avenue corner Sapphire Road
 
February 17, 2010
View along Emerald Avenue corner Garnet Road
Ongoing works at P4 level, view along Emerald Avenue corner Sapphire Road
 
January 6, 2010
View along Emerald Avenue corner Garnet Road
Ongoing works at P3 level
 
December 22, 2009
View along Emerald Avenue corner Garnet Road
Ongoing works at P3 level
 
November 13, 2009
Ongoing works at basement
Ongoing works at basement
 
October 29, 2009
View along Emerald Avenue corner Garnet Road
Ongoing works at basement
 
October 14, 2009
View along Emerald Avenue corner Garnet Road
Installation of Rebar
 
September 17, 2009
Installation of Rebar
Installation of Rebar
 
August 26, 2009
Installation of Rebar
Installation of Rebar
 
August 12, 2009
Ongoing excavation work
Ongoing excavation work
 
July 22, 2009
Ongoing excavation work
Ongoing excavation work
 
July 2, 2009
Ongoing excavation work
Ongoing excavation work
 
June 18, 2009
Ongoing excavation work
Ongoing excavation work
 
June 2, 2009
Ongoing excavation work
Ongoing excavation work
 
May 19, 2009
Ongoing excavation work
Ongoing excavation work
 
May 5, 2009
Ongoing excavation work
Ongoing excavation work
 
April 16, 2009
Ongoing excavation work
 
 
March 19, 2009
Ongoing excavation work
Ongoing excavation work
 
February 18, 2009
Ongoing excavation work
 
 
January 29, 2009
Ongoing excavation work
 
 
January 13, 2009
Ongoing excavation work
 
 
January 6, 2009
Ongoing excavation work
Ongoing excavation work
 
Ongoing excavation work
Ongoing excavation work
 
December 17, 2008
Ongoing excavation work
 
 
December 3, 2008
Ongoing excavation work
 
 
November 21, 2008
Excavation along Emerald Road
View from Adjacent Lot
 
November 14, 2008
Excavation along Garnet Road & Adjacent Lot
Excavation along Emerald Road
 
View from Adjacent Lot
 
 
November 10, 2008
Excavation Along Garnet Road
Excavation Along Garnet Road
 
Excavation Along Emerald Avenue